Stored total amount of high level waste (in tonnes heavy metals)
Note: Stored total amount of high level waste (in tonnes heavy metals)
IAEA (2003) K. Fukuda, W. Danker, J.S. Lee, A. Bonne, M.J. Crijns; IAEA Overview of global spent fuel storage; Vienna : IAEA, Department of Nuclear Energy, 2003
NEA (2007) Nuclear Energy Agency (NEA); Nuclear Energy Data : 2007 Edition = Données sur l' énergie nucléaire; Paris, France : OECD, 2007
NEA (2008) Nuclear Energy Agency (NEA); Nuclear Energy Data : 2008 Edition = Données sur l' énergie nucléaire; Paris, France : OECD, 2008
Historic series in spent fuel arising (tonnes heavy metals)
Note: Historic series in spent fuel arising (tonnes heavy metals)
OECD (2007) OECD environmental data compendium, part 1, chapter 8; April 2007 http://www.oecd.org/dataoecd/60/46/38106824.xls
IAEA (2003) K. Fukuda, W. Danker, J.S. Lee, A. Bonne, M.J. Crijns; IAEA Overview of global spent fuel storage; Vienna : IAEA, Department of Nuclear Energy, 2003
NEA (2007) Nuclear Energy Agency (NEA); Nuclear Energy Data : 2007 Edition = Données sur l' énergie nucléaire; Paris, France : OECD, 2007
NEA (2008) Nuclear Energy Agency (NEA); Nuclear Energy Data : 2008 Edition = Données sur l' énergie nucléaire; Paris, France : OECD, 2008
EU Electricity production from nuclear (percentages relative to 1990 level)
Note: EU Electricity production from nuclear (percentages relative to 1990 level)
Eurostat, Supply, transformation, consumption - electricity - annual data. http://appsso.eurostat.ec.europa.eu/nui/show.do?dataset=nrg_105a&lang=en
OECD (2007) OECD environmental data compendium, part 1, chapter 8; April 2007 http://www.oecd.org/dataoecd/60/46/38106824.xls
IAEA (2003) K. Fukuda, W. Danker, J.S. Lee, A. Bonne, M.J. Crijns; IAEA Overview of global spent fuel storage; Vienna : IAEA, Department of Nuclear Energy, 2003
NEA (2007) Nuclear Energy Agency (NEA); Nuclear Energy Data : 2007 Edition = Données sur l' énergie nucléaire; Paris, France : OECD, 2007
NEA (2008) Nuclear Energy Agency (NEA); Nuclear Energy Data : 2008 Edition = Données sur l' énergie nucléaire; Paris, France : OECD, 2008
Availability improvements in nuclear power plants in Europe
Note: Availability improvements in nuclear power plants in Europe
IAEA (2009) Power Reactor Information System (PRIS); August 2009 http://www.iaea.or.at/programmes/a2/
Numbers of Nuclear Fuel Cycle Facilities operational in 2009
Note: Numbers of Nuclear Fuel Cycle Facilities operational in 2009
NFCIS (2009) Nuclear Fuel Cycle Information System (NFCIS). August 2009 http://www-nfcis.iaea.org/
[1] The information refers to the quantity of heavy metals in nuclear fuel, which make up approximately 85% of the uranium fuel and 60% - 70% of the aggregation of fuel and fuel casing (fuel assembly).
Indicative specifications for different reactor types
The amount of spent fuel arising in Europe is not equivalent to the amount of high level waste that is ultimately stored, since part of this spent fuel is reprocessed. Former Eastern bloc member states appear to have exported part of their produced spent fuel to Russia, with Bulgaria appearing to have exported spent fuel as late as 2006 (Bellona, 2008).
Reprocessing is an important part of the fuel cycle within the European nuclear fuel industry, as illustrated by the share of European reprocessing facilities to the global total number of facilities (see Figure 5). Europe imports most of the uranium consumed by its nuclear power plants as ore, having very little mining production in the region itself. This means that the environmental and human health impact associated with uranium mining play a much lesser role in the European context. Imported ore is processed into fuel in Europe and part of the produced fuel is exported to the USA. While in other parts of the world the fuel is stored after consumption, in Europe a significant portion of the spent fuel is reprocessed, hence reducing the amount of high level waste that will require final disposal. For more technical details on spent fuel reprocessing see (EdF, 2007), (Harvard, 2003) and (MIT, 2003) and the International Atomic Energy Agency. Spent fuel from France, Japan, Netherlands, and Belgium is reprocessed in La Hague.. As of 1st January 2007, 22,650 metric tonnes of spent fuel have been treated at La Hague (Areva, 2007). Most reprocessed uranium (RepU) is not reused but stored on site or exported to Russia. An estimated total of 20 ktonnes of RepU is stored in France, produced by the different La Hague and the older Marcoule plants. Another 10 ktonnes has also purportedly been exported to Russia for permanent storage[1] (Burnie, 2007)
Spent nuclear fuel is the most highly radioactive waste. It decays rapidly at first, i.e. after 40 years the level of radioactivity has typically dropped to 1/1000th of the initial value. But it takes around 1000 years to drop to the level of the original uranium ore which was needed to produce that quantity of spent fuel (WNA, 2003). The potential impact of high level nuclear waste on humans and the environment depends on the level of radioactivity and on the conditions under which the waste is managed. The majority of member states currently store spent fuel and other high level radioactive wastes in above ground storage facilities. However, deep geological disposal in an underground repository is currently favoured as a long-term option by many countries. Lower level radioactive wastes are commonly stored in surface disposal sites.
[1] The information source uses the word “dumping” so it is assumed that this export to Russia is meant for permanent storage.
Costs of nuclear power production are a subject of intense discussion and estimates range from very low costs of e.g. 2 €ct/kWhe to more than 10 €ct/kWhe (ECN, 2007). Production cost estimates for the intended EPR (European Pressurised Reactor) power plants in France amount to €ct 4,6/kWhe. Differences between estimated production costs are mainly due to differences in the applied depreciation methodology, depreciation period and interest rates. For investment costs a fairly narrow range is mentioned. Costs for insurance may make up 30% of total operational costs. Dismantling costs are covered by a fund created from sales during the operational lifetime of the plant.
Estimated operational costs range from €ct1,2/kWhe to €2,0/kWhe, including dismantling and waste disposal. Costs for insurance may make up 30% of total operational costs. Cost estimates for final disposal of spent fuel in Finland (5,600 tonnes HM) are estimated in table above.
Nuclear power being a base load power production technology competes primarily with coal and large scale hydropower. Compared to coal a new NPP requires approximately twice the investment for the same capacity, excluding construction interests. Operational costs for a new coal power plant amount to approximately €ct 2/kWhe, including fuel costs (€ 2/GJ) (CE, 2006). In Europe, the nuclear industry still benefits from state subsidies but accurate, transparent information on the level of these subsidies is not available. A recent study conducted by DG Environment on “Environmental harmful subsidies” (EC, 2009) shows for instance that in Germany, the key subsidy specific to the decommissioning of nuclear-power facilities is a reduction in tax liabilities stemming from collection of decommissioning funds. Also the nuclear fuel is not taxed. The total size of this tax benefit is estimated at 5.6 billion EUR per year or 175 million EUR per nuclear power plant.
The indicator measures spent nuclear fuel arising from nuclear electricity production in the Member States that had nuclear powered electricity production capacity between 1990 and 2009 (data for Bulgaria missing). It provides an indication of the situation of radioactive waste accumulation and storage.
Original measurement units:
Spent fuel: tonnes of heavy metal (tHM)
Nuclear electricity generation: terawatt hours (TWh)
According to the World Energy Council http://www.worldenergy.org nuclear waste falls into the following four broad categories:
HLW accounts for 10% by volume of radioactive waste generated and contains about 99% of the total radioactivity. This includes fission products and spent fuel.
Spent fuel: tonnes of heavy metal (tHM)
Nuclear electricity generation: terawatt hours (TWh)
Decisions concerning the use of nuclear energy are up to Member States: the principle of subsidiary grants member states autonomy in deciding their energy mix.
Public concern about environmental and safety considerations has led to plans to phase out nuclear power in certain Member States (such as Germany, Spain, Sweden and Belgium), with some others either declaring or considering moratoria on the building of new nuclear plants. On 30th May 2011, the German government decided to stand by the previous government’s plans to close all reactors by 2022 (WNA 2011). Italy completely phased-out nuclear power following a referendum in 1987. In Sweden the Barseback nuclear power plant closed in 2005. Sweden is the only country to have a tax discriminating against nuclear power.
On the other hand, some Member States are currently discussing the construction of new nuclear capacity. In Finland (Olikiluoto-3) and France (Flamanville-3), the process of building additional capacity, based on new nuclear designs such as the European Pressurised Water Reactor (EPR), is ongoing. Both are planned to start-up in 2012. Furthermore, in Romania, the Cernavoda 2 reactor was completed in 2007. Meanwhile, several countries, like the Netherlands, Belgium and Hungary have decided to extend the life-time of existing NPPs. Lithuania, Latvia, Estonia and Poland agreed in 2007 on the construction of a NPP (Visaginas) in Lithuania. The Advanced Boiling Water Reactor is expected to operate from 2020. Bulgaria also plans to build two new reactors (Belene 1 and 2) and there has been strong governmental support for nuclear. The most up to date information on NPPs can be found in the Power Reactor Information System (PRIS) of the IAEA (IAEA, 2009).
On June 25th 2009 the European Council adopted Directive for setting up a Community framework for nuclear safety (COM(2008) 790 final). The Directive is a major step for achieving a common legal framework and a strong safety culture in Europe.
The Euratom Treaty helps to pool knowledge, infrastructure and funding of nuclear energy. It ensures the security of atomic energy supply within the framework of a centralised monitoring system.
Provides binding legal force to the main international nuclear safety standards (IAEA Safety Fundamentals and the Convention on Nuclear Safety). The Directive also reinforces the independence and resources of the national competent regulatory authorities.
National responsibility of Member States for the nuclear safety of nuclear installations is the fundamental principle on which nuclear safety regulation has been developed at the international level, as endorsed by the Convention on Nuclear Safety. That principle of national responsibility, as well as the principle of prime responsibility of the licence holder for the nuclear safety of a nuclear installation under the supervision of its national competent regulatory authority, should be enhanced and the role and independence of the competent regulatory authorities should be reinforced by this Directive.
States the fundamental safety objective as being to protect people and the environment from harmful effects of ionizing radiation. Ten safety principles are stated and their intent and purpose are briefly explained. The safety objective and the ten safety principles provide the grounds for establishing requirements and measures for the protection of people and the environment against radiation risks, and for the safety of facilities and activities that give rise to radiation risks.
Achieve and maintain a high level of nuclear safety worldwide through the enhancement of national measures and international co-operation including, where appropriate, safety-related technical co-operation; to establish and maintain effective defences in nuclear installations against potential radiological hazards in order to protect individuals, society and the environment from harmful effects of ionizing radiation from such installations; to prevent accidents with radiological consequences and to mitigate such consequences should they occur.
This will support three Generation IV reactors as part of a wider programme to promote low-carbon technologies. Of particular focus is the Astrid sodium-cooled fast reactor (France), the allegro gas-cooled fast reactor (central and eastern Europe) and the lead-cooled fast reactor (Belgium), and additional nuclear applications include hydrogen production, desalination plants and industrial heat.
No targets have been specified
Average annual rate of growth calculated using: [(last year / base year) ^ (1 / number of years) - 1]*100
No methodology for gap filling has been specified. Probably this info has been added together with indicator calculation.
No methodology references available.
For the production of electricity, data have traditionally been compiled by Eurostat through the annual Joint Questionnaires (although there is no separate questionnaire for nuclear energy), shared by Eurostat and the International Energy Agency, following a well-established and harmonised methodology. This year for the first time greater disaggregation is available in Eurostat and we have aggregated the product codes (107030, 31, 32, and 33) to calculate gross electricity generation from nuclear power (former product code 107003). The primary energy from nuclear is calculated based on the electricity generation from nuclear with a 33.3 % efficiency rate. Methodological information on the annual Joint Questionnaires and data compilation can be found on Eurostat's website in the section on metadata on energy statistics http://epp.eurostat.ec.europa.eu/portal/page/portal/statistics/metadata, also see information related to the Energy Statistics Regulation from the same link.
Data on spent fuel arisings have been compiled by the OECD using data from member Governments. This is a consistent ongoing process that is updated annually. However, no information is available for Bulgaria. During 2008 and 2009, no data was available for Lithuania, Romania, Slovenia and Sweden, which decreases the overall accuracy of the indicator. The use of spent fuel arisings as a proxy for overall radioactive waste is itself slightly uncertain because of the various inconsistencies in classification of radioactive waste between Member States, although it does provide a ‘reliable representation of the production of radioactive waste situation and its evolution over time’ (OECD, 1993).
No uncertainty has been specified
For references, please go to https://www.eea.europa.eu/data-and-maps/indicators/nuclear-energy-and-waste-production/nuclear-energy-and-waste-production-1 or scan the QR code.
PDF generated on 18 Apr 2024, 05:03 AM
Engineered by: EEA Web Team
Software updated on 26 September 2023 08:13 from version 23.8.18
Software version: EEA Plone KGS 23.9.14
Document Actions
Share with others